Projects

Approved Phase One Projects

After Measure G passed, the Bond Implementation Committee (BIC), a Superintendent’s Advisory Committee formed in December of 2016, began its work. The committee was comprised of over 40 members representing all schools, departments, internal groups, as well as community members that support education. Members included teachers, staff, students, parents, school site and District administration, Board members, representatives from local agencies/partners, as well as members of the community.

The committee was given three responsibilities during the process – 1) To advise the Superintendent on the prioritization of projects to help him make a recommendation to the Board, 2) To act as liaisons to sites and the local community for the work being performed, and 3) To act in the best interest of the District as a whole, not just for the member’s site or constituency group.  Using the Measure G Bond language and the Facilities Master Plan to guide the process, the committee met several times, prioritized the projects by need and value, and made their recommendation to the Superintendent for Phase 1 projects (first $105 million) and Phase 2 projects (remaining $100 million scheduled after 2021).  District staff then used the feedback from the committee, as well as discussions with their architects and construction management firm, to complete the final proposed list. In May and August of 2017, the Board of Trustees approved the initial list of 15 projects covered in Phase 1.

Throughout the Fall of 2018, the Board of Trustees at regular Board meetings received presentations from District staff on cost escalation issues facing Measure G project prioritization.  Two years of devastating fires in California, steel tariffs and $250 billion of construction bond issuance throughout the state put tremendous pressure and competition on construction costs.  In order to maximize project priorities and minimize project escalation, the Board voted to delay work on some Phase 1 projects to the next funding cycle in 2021/2022. These projects include the SMHS 2nd Turf Field, Lynwood Remodel, Sinaloa Gym, and a percentage of the allocation for the Classroom Technology Tool Kit, Flexible Furniture, and IT Infrastructure.**  The Board also, after much community discussion, voted to insert into Phase 1 HVAC upgrades at Lynwood ES, Olive ES and Loma Verde ES, as well as the construction of an Athletic Field Complex at Novato HS.

Over several meetings in the Spring and Fall of 2019, the Board reviewed Phase 2 allocation methodologies and recommendations in order to begin the project prioritization process for remaining Bond projects.  At the December 3, 2019 and January 14, 2020 meetings, the Board allocated the remaining Measure G funds into categorical designations. District standards and a prioritized project list for those categories will be developed throughout 2022, and recommendations made to the Superintendent for Phase 2 projects for presentation to the Board for approval.

District Wide

Your Content Goes Here

Your Content Goes Here

Your Content Goes Here

Hamilton Re-Roof Project

Loma Verde Exterior Painting Project

Lu Sutton Exterior Painting Project

Lynwood Skylight Replacement

Novato High Stadium Returf and Track Resurfacing

Novato High Re-Roof Project

San Jose MS Library HVAC Replacement

San Jose Re-Roof Project

San Marin High Stadium Returf and Track Resurfacing

San Marin High Exterior Finish Replacement

San Ramon ES Re-Roof Project

Sewer Repairs:  Novato HS, Olive ES, San Ramon ES, Lu Sutton, Loma Verde, Hamilton

Site Specific

Project scope is for a campus modernization, including moving the District’s food distribution services off of the school site, and new construction of a 4900 ft2 four-classroom building, 1,440 ft2 Pre-K classroom and a 2,500 ft2 community center.

Phase 1: District Food and Nutritional Services (FANS) Move to Olive Ave. Warehouse

This project renovated the space to be vacated by Maintenance and Operations at the Olive Ave. warehouse, to relocate the Food & Nutritional Services (FANS) operation off of the Lynwood campus. The project began in the summer of 2019 and was fully completed in January 2020.

Phase 2: Campus-wide Classroom Modernization and New Elementary School Kitchen

This project renovated the interiors of all classroom spaces with new flooring, lighting, paint, and built in cabinetry;  provided new classroom furniture; upgraded the IT Infrastructure throughout the campus; added a Classroom Technology toolkit;  painted the exterior of the campus and constructed a new right-sized elementary school kitchen. Project completion was March, 2022.

Originally an element of the approved Lynwood Campus Remodel project, the classroom air-conditioning portion was redirected for completion in 2019. This project will replace existing gas furnaces with energy-efficient electric heat-pumps and exterior condensing units. This new system provides both heating and much needed cooling capacity in each classroom. The project also includes increased electrical capacity in new conduit runs for the new heat pump units. The new HVAC system is 100% compatible with the District’s existing Pelican climate control wireless thermostat technology, avoiding additional project costs. HVAC project slated to be completed over the summer 2019.

This project will involve replacing the existing gas heating unit/furnace from each classroom with a new energy-efficient heat pump and exterior condensing unit. This new system will provide both heating and much needed cooling capacity in each classroom. The project also includes increased electrical capacity in new conduit runs for the new heat pump units. The new HVAC system is 100% compatible with the District’s existing Pelican climate control wireless thermostat technology, avoiding additional project costs. HVAC project is slated to be completed over the summer 2019.

Designed by WLC Architects, this project constructs a brand new 450-seat, 18,000 ft2  Center for the Arts, including gallery space, classroom/greenroom spaces and support spaces. This balcony-style seating facility will support District-wide arts programs, as well as Novato High School’s Marin School for the Arts. Scheduled to break ground in June of 2019, this project, being constructed on the current tennis court footprint, is projected for completion early 2021.

Scheduled for groundbreaking in June 2019, this project constructs a brand new 15,000 ftCenter for the Sciences to replace aging portable classrooms at the end of their useful life. The new building will house 10 lecture/labs, a demonstration area, breakout spaces, staff support space, as well as outdoor learning areas to support project-based learning pedagogy. Completion targeted for Fall of 2020.

This project constructs a new 85,000 ft2 synthetic turf practice field, relocates and constructs a new 31,000 ft2 synthetic turf softball field, reshapes a 102,000 ft2 turf baseball field, and builds 30,240 ft2 of new tennis courts (5).  Carducci & Associates is the landscape architect designing this new facility which will support student physical education and team sports in a safe environment available for year-round use. Completion expected December of 2019.

This project will involve replacing the existing gas heating unit/furnace from each classroom with a new energy-efficient heat pump and exterior condensing unit. This new system will provide both heating and much needed cooling capacity in each classroom. The project also includes increased electrical capacity in new conduit runs for the new heat pump units. The new HVAC system is 100% compatible with the District’s existing Pelican climate control wireless thermostat technology, avoiding additional project costs. HVAC project slated to be completed over the summer 2019.

This project renovated the interiors of all classrooms, including new paint, flooring, lighting, built in cabinetry; provided new classroom furniture; upgraded the IT Infrastructure throughout the campus and added a new Fire Alarm and Clock Bell system; added a Classroom Technology toolkit; painted the exterior of the campus; renovated prior administration space into a new Kindergarten classroom and workspace; and built a new Administration building, reorienting the front of the school to Olive Avenue. Project expected to be complete June 2022.

This project builds a new right-sized Elementary School Kitchen on campus. Project construction to begin June 2022.

This project will replace existing gas furnaces with energy-efficient electric heat-pumps and exterior condensing units. This new system provides both heating and much needed cooling capacity in each classroom. The project also includes increased electrical capacity in new conduit runs for the new heat pump units. The new HVAC system is 100% compatible with the District’s existing Pelican climate control wireless thermostat technology, avoiding additional project costs. Project construction to begin June 2022.

Replacing a 50-year old hexagonal cafeteria building currently housing the Performing Arts program, this project constructs a new 7,800 ft2 Performing Arts Center in its place, accommodating approximately 250 seats, with greenroom/classroom support spaces, lobby, ticket booth, and restrooms. Project is scheduled to begin in the summer of 2019, with a targeted completion date in early 2021

Quatrocchi Kwok Architects designed a new state of the art 18,000 ft2 STEM (Science, Technology, Engineering, and Math) classroom/laboratory building, including student break-out spaces, demonstration areas, and staff support space. Replacing aging classroom portables, the building will support San Marin’s STEM program, including two dedicated BioTechnology classroom/labs as well as a positive pressure clean room. Breaking ground in June 2019, this project is targeted for completion in the Fall of 2020.

This project replaced the existing softball and baseball grass fields with synthetic turf fields that include new backstops, dugouts, and bullpens. Project was completed in May, 2022

This project installs a new stadium public address/sound system, providing a dramatic improvement over the existing stadium PA system. Project was done in conjunction with the Stadium Lights Project in order to provide a costs savings for work required for the PA system (Any expenses going toward the Stadium Lights project are not paid for by Measure G).

This project, completed over the summer of 2018, involved replacing the existing gas heating unit/furnace from each classroom with a new energy-efficient heat pump and exterior condensing unit. This new system provides both heating and much needed cooling capacity in each classroom. The project also included increased electrical capacity in new conduit runs for the new heat pump units. The new HVAC system is 100% compatible with the District’s existing Pelican climate control wireless thermostat technology, avoiding additional project costs.

This  modernization project includes a new kitchen, gymnasium renovation, exterior siding renovation, and fire alarm/clock bell system upgrade. Construction scheduled to begin Summer 2022.

This multi-step project constructs a new 10,800 ft2 warehouse building on C Street to relocate Maintenance & Operations from the Olive Ave. warehouse and relocates Grounds from the Novato HS campus, as required by the Novato Center for the Sciences project. Once relocated, this project then renovates the vacant space at the Olive Ave warehouse to relocate the Food & Nutritional Services (FANS) operation, as part of the Lynwood Campus remodel. The project is scheduled to begin in the summer of 2019; the FANS portion is targeted for an August 2019 completion and the new Maintenance facility is targeted for a November 2019 completion date.